Name of the Experiment
|
Determination
of Bearing capacity of soil using
Plate
load test
|
||||||||||||
Theory
|
|||||||||||||
Bearing
capacity is the capacity of soil to support the loads applied to the ground.
The bearing capacity of soil is the maximum average contact pressure between
the foundation and the soil which should not produce shear failure in the
soil.
|
|||||||||||||
List of Equipment needed
|
|||||||||||||
Bearing Plates:
Consist of mild steel 75 cm in diameter and 0.5 to 2.5 cm thickness and few
other plates of smaller diameters (usually 60, 45, 30 and 22.5 cm) used as
stiffeners.
Loading equipment:
Consists of a reaction frame and a hydraulic jack. The reaction frame may
suitably be loaded to give the needed reaction load on the plate.
Settlement Measurement: Three or four dial gauges fixed on the periphery of the bearing
plate. The datum frame should be supplied for from the loading area.
|
|||||||||||||
Procedure
|
|||||||||||||
1. Test pit should be at least 4 times as wide as the plate and
to the foundation depth to be placed. 2. The test shall be carried out at the
same level of the proposed foundation level or as directed by the Engineer
while the same conditions to which the proposed foundation will be subjected
should be prepared if possible.
3. At least three (3) test locations are required for
calibration on size effect of test plates, and the distance between test
locations shall not be less than five (5) times the diameter of the largest
plate used in the tests The test surface should be undisturbed, planar and
free from any crumbs and loose debris.
4. When the test surface is excavated by machinery, the
excavation should be terminated at 200mm to 300mm above the test surface and
the test surface should be trimmed manually.
5. To ensure even transference of the test load on to the test
surface, the steel plate should be leveled and have full contact with the
ground. Sand filling or cement mortar or plaster of Paris could level small
uneven ground surface. If the test is carried out below the groundwater
level, it is essential to lower the groundwater level by a system of wells or
other measures outside and below the test position.
6. The preparation of the test surface may cause an unavoidable
change in the ground stress which may result in irreversible changes to the
subsoil properties. It is essential that the exposure time of the test
surface and the delay between setting up and testing should be minimized.
7. The time lag shall be reported with the test result. Support
the loading platforms or bins by cribbing or other suitable means, at points
as far removed from the test area, preferably not less than 2.4m.
8. The total load required for the test shall be available at
the site before the test is started. The support for the beam with dial
gauges or other settlement-recording devices shall not less than 2.4m from
the center of the loaded area.
9. Mackintosh Probe Test to be carried out at load test location
(center of plate) at testing level before the test for calibration purpose.
10. Loading shall be applied in 3 cycles. The time interval of
each stage of loading should not less than 15 minute. Longer time interval is
required at certain specified loading stages. The settlement at each stage of
loading should be taken at the interval of every 15 minutes before and after
each load increment.
11. If the required time interval is more than 60 minutes, the
reading shall be taken at every 15 minutes interval. In the load measurement,
the test record sheet should include the targeted load schedule, load cell
readings (primary measurement) & pressure gauges readings (secondary
measurement).
12. The testing contractor shall control the loading using load
cell readings to achieve the targeted load in each stage of loading &
record the actual readings in the load cell & the pressure gauge
simultaneously.
13. Continue each test until a peak load is reached or until the
ratio of load increment to settlement increment reaches a minimum, steady
magnitude.
14. If sufficient load is available, continue the test until the
total settlement reaches at least 10 percent of the plate diameter, unless a
well-defined failure load is observed.
|
|||||||||||||
Observation and Tabulation
|
|||||||||||||
|
|||||||||||||
Calculation
|
|||||||||||||
Determine
the settlement of footing using the following relationship
Sf = Sp {[B
(Bp + 0.3) ]/[ Bp (B + 0.3) ]}^2
Where,
B = width of footing in mm. Bp = width of test plate in mm. Sp= settlement of test plate in mm. Sf = settlement of footing in mm. |
|||||||||||||
Result and Discussion
|
|||||||||||||
Bearing capacity of soil ___________________,
Settlement of Footing ____________
|
Monday, 6 August 2018
Determination of Bearing capacity of soil using Plate load test
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment